Half of the studio now has a laminate (fake) hardwood floor and trim. It has been swept and cleaned and is ready for regular use. It isn't 100% finished, but I have just one more weekend of work to get there.
Here's what's left:
- Paint window and floor molding
- Hang window treatments
- Install PVC utility grid
For the bathroom/make-up room all that is left is:
- Paint cabinet bases
- Put down floor (contractor will do that next week)
- Install toilet and hook up plumbing (contractor will that after the floor guy)
- Paint cabinet bases
- Decorative finish on walls
- Hang mirrors
- Put misc. bathroom hardware